The county is approving a contract change with Traffic Systems Construction, Inc. for the intersection improvement project at Morton Ranch Road and Old Katy Hockley Cut Off Road, adding 219 days to the schedule and $25,294.34 to the contract price.
What it means for you
Construction at this Precinct 4 intersection will take longer and cost slightly more than originally contracted.
Outcome
A motion was made by Commissioner Ellis, seconded by Commissioner Garcia, that this item be approved. The motion carried by the following vote: (5-0)
How each member voted
Lina Hidalgo (County Judge): AyeRodney Ellis (Commissioner, Precinct 1): AyeAdrian Garcia (Commissioner, Precinct 2): AyeTom S. Ramsey (Commissioner, Precinct 3): AyeLesley Briones (Commissioner, Precinct 4): Aye
5–0, per the official record.