ON THE AGENDAHarris County Commissioners Court · 2025-12-11

The Court is asked to accept a certificate of substantial completion for Phase 2 of the Lauder Stormwater Detention Basin project in the Greens Bayou Watershed, performed by Lecon, Inc.

What it means for you

If accepted, the record formally acknowledges that Phase 2 of the Lauder Stormwater Detention Basin constructed by Lecon, Inc. has been substantially completed.

Outcome

This item was accepted.

Drainage & flooding — see all →Greens Bayou Watershed, Precinct 2

Official source

Official meeting record — Harris County Legistar ↗

The record does not attribute individual votes for this item — most items pass by named consensus rather than a contested roll call.

Quick answersfrom the official record
Who benefits?Lecon, Inc.Legistar record ↗
Who decides?Decided by a vote of the Harris County Commissioners Court. Flood Control District brought it forward. Taken up at the December 11, 2025 meeting — no outcome recorded yet.Legistar record ↗
The official caption doesn't name a dollar amount or who repays it — full details in the official Legistar record ↗

Cite this: https://plaindocket.com/item/real-hc25-7836-175839 — data from official records via PlainDocket.