PASSEDHarris County Commissioners Court · 2026-01-08

The county is approving a contract change with Environmental Allies, Inc. for the Goforth Detention Basin Enhancement project that adds 21 calendar days to the schedule with no change in cost.

What it means for you

The contractor gets more time to finish drainage basin work in Precinct 3; residents in that area may see the project completed slightly later than originally planned.

Outcome

A motion was made by Commissioner Garcia, seconded by Commissioner Ellis, that this item be approved. The motion carried by the following vote: (5-0)

How each member voted

Lina Hidalgo (County Judge): AyeRodney Ellis (Commissioner, Precinct 1): AyeAdrian Garcia (Commissioner, Precinct 2): AyeTom S. Ramsey (Commissioner, Precinct 3): AyeLesley Briones (Commissioner, Precinct 4): Aye

5–0, per the official record.

Official source

Official meeting record — Harris County Legistar ↗

The record includes an individually-attributed vote for this item, shown above.

Quick answersfrom the official record
Who's paid?Environmental Allies, Inc.Legistar record ↗
Who decides?Decided by a vote of the Harris County Commissioners Court. Taken up at the January 8, 2026 meeting — Adopted.Legistar record ↗
The official caption doesn't name a dollar amount or which fund pays for it — full details in the official Legistar record ↗