PASSEDHarris County Commissioners Court · 2026-02-12

The county is approving a separate contract change with CE Barker, LTD for the same Westfield Estates sanitary sewer construction project, adding $35,737.22 to the contract.

What it means for you

This adds further costs to the sewer construction project serving the Westfield Estates area of Precinct 2.

Outcome

A motion was made by Commissioner Garcia, seconded by Commissioner Ellis, that this item be approved. The motion carried by the following vote: (5-0)

How each member voted

Lina Hidalgo (County Judge): AyeRodney Ellis (Commissioner, Precinct 1): AyeAdrian Garcia (Commissioner, Precinct 2): AyeTom S. Ramsey (Commissioner, Precinct 3): AyeLesley Briones (Commissioner, Precinct 4): Aye

5–0, per the official record.

Utilities — see all →Westfield Estates, Precinct 2

Official source

Official meeting record — Harris County Legistar ↗

The record includes an individually-attributed vote for this item, shown above.

Quick answersfrom the official record
How much?$35,737Legistar record ↗
Who's paid?CE Barker, LTDLegistar record ↗
Who decides?Decided by a vote of the Harris County Commissioners Court. Taken up at the February 12, 2026 meeting — Adopted.Legistar record ↗
The official caption doesn't name which fund pays for it — full details in the official Legistar record ↗