ON THE AGENDAHarris County Commissioners Court · 2026-05-14

The Court is asked to accept a certificate of substantial completion for the Mercer Stormwater Detention Basin project in the Cypress Creek Watershed, completed by Arrowstone Contracting LLC.

What it means for you

If accepted, it formally recognizes that Arrowstone Contracting LLC has substantially finished construction of the Mercer stormwater detention basin, a flood-control project in Precinct 1.

Outcome

This item was accepted.

Drainage & flooding — see all →Cypress Creek Watershed, Precinct 1

Official source

Official meeting record — Harris County Legistar ↗

The record does not attribute individual votes for this item — most items pass by named consensus rather than a contested roll call.

District A — Amy PeckADistrict B — Tarsha JacksonBDistrict C — Joe PanzarellaCDistrict D — Carolyn Evans-ShabazzDDistrict E — Fred FlickingerEDistrict F — Tiffany ThomasFDistrict G — Mary Nan HuffmanGDistrict H — Mario CastilloHDistrict I — Joaquin MartinezIDistrict J — Edward PollardJDistrict K — Martha Castex-TatumK

Official council district boundaries · City of Houston GIS. Tap a district to see who represents it.

Quick answersfrom the official record
Who benefits?Arrowstone Contracting LLCLegistar record ↗
Who decides?Decided by a vote of the Harris County Commissioners Court. Flood Control District brought it forward. Taken up at the May 14, 2026 meeting no outcome recorded yet.Legistar record ↗
The official caption doesn't name a dollar amount or who repays it — full details in the official Legistar record ↗

Cite this: https://plaindocket.com/item/real-hc26-2994-187896 — data from official records via PlainDocket.