The county is approving a contract change with Reliance Construction Services, LP that reduces the final construction contract by $75,770.10 for the water distribution system project on Olana Drive in Parkwood Estates Phase 4, Precinct 2.
What it means for you
The final cost of the Parkwood Estates Phase 4 water distribution system project in Precinct 2 is being reduced by $75,770.10.
Outcome
A motion was made by Commissioner Garcia, seconded by Commissioner Ramsey, that this item be approved. The motion carried by the following vote: (5-0)
How each member voted
Lina Hidalgo (County Judge): AyeRodney Ellis (Commissioner, Precinct 1): AyeAdrian Garcia (Commissioner, Precinct 2): AyeTom S. Ramsey (Commissioner, Precinct 3): AyeLesley Briones (Commissioner, Precinct 4): Aye
5–0, per the official record.