The county is approving a contract change with Environmental Allies, Inc. to add 45 calendar days to the Blackhawk Boulevard roadway project between Scarsdale Boulevard and Sam Houston Parkway in Precinct 2, with no change in the contract amount.
What it means for you
Construction on Blackhawk Boulevard in Precinct 2 will take 45 more days to complete, but the contract price is not changing.
Outcome
A motion was made by Commissioner Garcia, seconded by Commissioner Ramsey, that this item be approved. The motion carried by the following vote: (5-0)
How each member voted
Lina Hidalgo (County Judge): AyeRodney Ellis (Commissioner, Precinct 1): AyeAdrian Garcia (Commissioner, Precinct 2): AyeTom S. Ramsey (Commissioner, Precinct 3): AyeLesley Briones (Commissioner, Precinct 4): Aye
5–0, per the official record.