The Commissioners Court approved a one-year renewal of a contract with Epoxy Design Systems, Inc. to perform concrete repairs at the Washburn Tunnel, running from August 1, 2026 through July 31, 2027, at a cost of $890,708.62.
What it means for you
This keeps an existing contractor on the job maintaining the Washburn Tunnel, a road tunnel in Precinct 2, for another year.
Outcome
A motion was made by Commissioner Ellis, seconded by Commissioner Garcia, that this item be approved. The motion carried by the following vote: (5-0)
How each member voted
Lina Hidalgo (County Judge): AyeRodney Ellis (Commissioner, Precinct 1): AyeAdrian Garcia (Commissioner, Precinct 2): AyeTom S. Ramsey (Commissioner, Precinct 3): AyeLesley Briones (Commissioner, Precinct 4): Aye
5–0, per the official record.