ON THE AGENDAHarris County Commissioners Court · 2026-07-30

The Court is asked to approve awarding a CDBG-DR/CDBG-MIT funded construction contract to Takco, Inc. for $42,614,329 to build Phase 2 of the Genoa Red Bluff Stormwater Detention Basins for the Flood Control District, with a Minority- and Women-Owned Business Enterprise goal of 15.47%.

What it means for you

If approved, Takco, Inc. would construct a large stormwater detention basin in the Genoa Red Bluff area using federal disaster recovery and mitigation grant funds, aimed at reducing flood risk for nearby residents.

Outcome

This item was accepted.

Drainage & flooding — see all →Genoa Red Bluff area, Harris County

Official source

Official meeting record — Harris County Legistar ↗

The record does not attribute individual votes for this item — most items pass by named consensus rather than a contested roll call.

District A — Amy PeckADistrict B — Tarsha JacksonBDistrict C — Joe PanzarellaCDistrict D — Carolyn Evans-ShabazzDDistrict E — Fred FlickingerEDistrict F — Tiffany ThomasFDistrict G — Mary Nan HuffmanGDistrict H — Mario CastilloHDistrict I — Joaquin MartinezIDistrict J — Edward PollardJDistrict K — Martha Castex-TatumK

Official council district boundaries · City of Houston GIS. Tap a district to see who represents it.

Quick answersfrom the official record
How much?$42,614,329Legistar record ↗
Who's paid?Takco, Inc.; Harris County Flood Control DistrictLegistar record ↗
Who decides?Decided by a vote of the Harris County Commissioners Court. Office of the Purchasing Agent brought it forward. Taken up at the July 30, 2026 meeting no outcome recorded yet.Legistar record ↗
The official caption doesn't name which fund pays for it — full details in the official Legistar record ↗

Cite this: https://plaindocket.com/item/real-hc26-4837-193636 — data from official records via PlainDocket.