← Back to PlainDocket
PASSEDHarris County Commissioners Court · 2026-08-25

The county is approving a contract change with ECM Construction, LLC for the Fairmont Parkway Improvements project that adds 10 calendar days to the schedule and reduces the contract amount by $117,427.66.

What it means for you

The final construction contract for Fairmont Parkway in Precinct 2 is being adjusted, resulting in a cost deduction and a small extension to the project timeline.

Outcome

A motion was made by Commissioner Ramsey, seconded by Commissioner Garcia, that this item be approved. The motion carried by the following vote: (4-0)

How each member voted

Lina Hidalgo (County Judge): AbsentRodney Ellis (Commissioner, Precinct 1): AyeAdrian Garcia (Commissioner, Precinct 2): AyeTom S. Ramsey (Commissioner, Precinct 3): AyeLesley Briones (Commissioner, Precinct 4): Aye

40, per the official record.

Transportation — see all →Precinct 2 – Fairmont Parkway

Official source

Official meeting record — Harris County Legistar ↗

The record includes an individually-attributed vote for this item, shown above.

District A — Amy PeckADistrict B — Tarsha JacksonBDistrict C — Joe PanzarellaCDistrict D — Carolyn Evans-ShabazzDDistrict E — Fred FlickingerEDistrict F — Tiffany ThomasFDistrict G — Mary Nan HuffmanGDistrict H — Mario CastilloHDistrict I — Joaquin MartinezIDistrict J — Edward PollardJDistrict K — Martha Castex-TatumK

Official council district boundaries · City of Houston GIS. Tap a district to see who represents it.

Quick answersfrom the official record
How much?$117,428Legistar record ↗
Who's paid?ECM Construction, LLCLegistar record ↗
Which fund?deductionLegistar record ↗
Who decides?Decided by a vote of the Harris County Commissioners Court. Taken up at the August 25, 2026 meeting Adopted.Legistar record ↗

Cite this: https://plaindocket.com/item/real-hc26-5495-195618 — data from official records via PlainDocket.

The county is approving a contract change with ECM Construction, LLC for the Fairmont… — PlainDocket