The county would approve a contract change with Statewide Traffic Signal Company that adds 60 calendar days and reduces the final payment by $126,493.80 for completed intersection improvements at Hufsmith Road at FM 2978, Stuebner Airline Road, and Kuykendahl Road.
What it means for you
This is a closeout adjustment for a completed intersection improvement project in Precinct 3, extending the contract timeline and reducing the final amount owed.
Outcome
A motion was made by Commissioner Ellis, seconded by Commissioner Garcia, that this item be approved. The motion carried by the following vote: (5-0)
How each member voted
Lina Hidalgo (County Judge): AyeRodney Ellis (Commissioner, Precinct 1): AyeAdrian Garcia (Commissioner, Precinct 2): AyeTom S. Ramsey (Commissioner, Precinct 3): AyeLesley Briones (Commissioner, Precinct 4): Aye
5–0, per the official record.