ON THE AGENDAHarris County Commissioners Court · 2026-09-17

The Court is asked to approve a contract change with SER Construction Partners, LLC for the Houmont Park Subdivision drainage improvements project that would add 4 calendar days and increase the contract amount by $16,063.25.

What it means for you

If approved, the contractor would have 4 more days to finish drainage work in the Houmont Park area in Precinct 1, and the county would pay an additional $16,063.25 from the HC Road Fund.

Outcome

No disposition recorded yet.

Drainage & flooding — see all →Precinct 1 – Houmont Park Subdivision

Official source

Official meeting record — Harris County Legistar ↗

The record does not attribute individual votes for this item — most items pass by named consensus rather than a contested roll call.

Quick answersfrom the official record
How much?$16,063Legistar record ↗
Who's paid?SER Construction Partners, LLCLegistar record ↗
Which fund?HC Road Fund, additionLegistar record ↗
Who decides?Decided by a vote of the Harris County Commissioners Court. Taken up at the September 17, 2026 meeting no outcome recorded yet.Legistar record ↗

Cite this: https://plaindocket.com/item/real-hc26-5957-198316 — data from official records via PlainDocket.