PASSEDHarris County Commissioners Court · 2026-11-12

The court approved the first contract change with Dominion Construction & Supply PLLC for a stormwater detention basin along Jackson Bayou, adding 3 calendar days and $10,805 to the contract.

What it means for you

The Jackson Bayou detention basin project in Precinct 3 gets a small time extension and cost increase, funded through federal CDBG-DR dollars.

Outcome

A motion was made by Commissioner Ellis, seconded by Commissioner Briones, that this item be approved. The motion carried by the following vote: (5-0)

How each member voted

Lina Hidalgo (County Judge): AyeRodney Ellis (Commissioner, Precinct 1): AyeAdrian Garcia (Commissioner, Precinct 2): AyeTom S. Ramsey (Commissioner, Precinct 3): AyeLesley Briones (Commissioner, Precinct 4): Aye

5–0, per the official record.

Drainage & flooding — see all →Precinct 3 – Jackson Bayou Watershed

Official source

Official meeting record — Harris County Legistar ↗

The record includes an individually-attributed vote for this item, shown above.

Quick answersfrom the official record
How much?$10,805Legistar record ↗
Who's paid?Dominion Construction & Supply PLLCLegistar record ↗
Which fund?CDBG-DR, additionLegistar record ↗
Who decides?Decided by a vote of the Harris County Commissioners Court. Taken up at the November 12, 2026 meeting — Adopted.Legistar record ↗