The Court is asked to approve a contract change with Mar-Con Services, LLC, adding 267 calendar days and $548,921.20 to the construction contract for the Miller Road 2 project (Wallisville Road to US 90) in Precinct 1.

What it means for you

If approved, Mar-Con Services would receive an additional $548,921.20 and 267 more days to finish the Miller Road 2 construction project in Precinct 1, with minority- and women-owned businesses currently performing 100% of the contracted work.

Outcome

No disposition recorded yet.

Transportation — see all →Miller Road 2, Wallisville Road to US 90, Precinct 1

Official source

Official meeting record — Harris County Legistar ↗

The record does not attribute individual votes for this item — most items pass by named consensus rather than a contested roll call.

Quick answersfrom the official record
How much?$548,921Legistar record ↗
Who's paid?Mar-Con Services, LLCLegistar record ↗
Who decides?Decided by a vote of the Harris County Commissioners Court. Taken up at the November 19, 2026 meeting — no outcome recorded yet.Legistar record ↗
The official caption doesn't name which fund pays for it — full details in the official Legistar record ↗